China Economic Net

Islamabad: Pakistani Prime Minister Imran Khan has pledged that there will be no more delay in execution of the China-Pakistan Economic Corridor (CPEC) projects.

Addressing a ceremony here in connection with the inauguration of Matiari to Lahore 600 KV transmission line completed under the CPEC, the PM maintained that some delay in implementation of the CPEC projects was due to Covid-19.

He vowed to accelerate the pace of work on projects being executed under the CPEC as the Covid-19 situation was improving.

Prime Minister Khan pointed out that the breakout of COVID-19 created some hurdles including disruption of supply chains which also increased prices of essential commodities.

“The situation is improving and progress will again be visible on the CPEC related projects as well as bringing down the inflation,” he contended.

The PM said the scope of the CPEC was now being expanded from power generation and road infrastructure projects to cooperation in the areas of industries and agriculture.

“The cooperation in these two important sectors will help Pakistan reduce the debt burden through wealth creation,” he added.

Regarding the Matiari-Lahore transmission line, the PM informed that this 886-kilometer long state-of-the-art transmission line will help reduce power losses.

Besides energy, the PM stated, other CPEC projects under Chinese President Xi Jinping’s Belt and Road Initiative relating to industrialization and innovation in agriculture would be launched in the next phase.

He hoped that completion of CPEC projects would lead to wealth creation and help the government pay off heavy debt.

Federal Minister for Energy Hammad Azhar said the project, which was made operational after testing it in three phases including the peak seasons, would help in removing the transmission bottleneck.

He underlined that the CPEC power projects were the important pillars of Pakistan’s economic system and were acting as “smart and efficient sources” of green energy generation.

Chinese Ambassador Nong Rong – terming the operationalization of 660 KV HVDC project a milestone – said Pakistan’s power grid system had now entered a new era of development and upgradation.

He pointed out that cheap electricity was key to socio-economic development of Pakistan and vowed that China would continue to extend its support in this regard.

He told the audience that the 886 km transmission line would go along 510 km of motorway and create around 70,000 jobs in the country.

President State Grid Corporation of China Xin Baoan in his video-link address to the ceremony said the 70th anniversary of Pakistan-China friendship was marked by cooperation at diverse levels for the benefit of their people.

He pledged that his corporation would work closely with its local counterparts in Pakistan on projects of energy cooperation.

The HVDC transmission line project will evacuate power from the upcoming coal-based thermal power plants located at Port Qasim, Hub and Thar, he added.

The National Electric Power Regulatory Authority (NEPRA) has already approved the total cost of the project of US $1,658 million (including taxes and insurance) and has issued a tariff determination of Rs.0.74 per kWh at the rate of US $ 1 (equal to Rs 104.4).

The monthly HVDC Line capacity charges for 4,000 MW are Rs 4.2 billion approximately (after indexation in tariff).

The project is being executed on Build, Own, Operate and Transfer (BOOT) basis for a 25 years term. The operation and maintenance of the converter stations will be carried out by Pak MLTC and that of the Transmission Line by NTDC.

The self-supported towers have been installed for bi-pole HVDC line with Quad Bundle Conductor and size of 4×1250 mm2.

The NEPRA has fixed the line availability factor of 98.5 percent and any non-availability beyond 1.5 pecent shall be penalized. The EPA (Environmental Protection Agency) of the Sindh government and Punjab government have issued No-Objection certificates for EIA (Environmental Impact Assessment).

The testing and commissioning of the project continued for more than one year and was completed on August 18, 2021 after its trial run for 168 hours along with capability demonstration tests.